Bond Projects

 
March 2024
 
New Air conditioning at Dana
 
February 2024

Master Plan
 
December 2023
 
$20 in state funding
 
October 2023
 
donation for auxiliary gym
 
September 2023
 
Judkins gym floor
 
August 2023

new landscaping at Oceano and Mesa
 
Cosmetology
 
June 2023
 
There are lots of summer projects
 
May 2023

New culinary building at AGHS
 
April 2023

New Classrooms at Fairgrove
 
March 2023
 
New classrooms at AGHS
 
 
January 2023
 
Dana Asphalt Improvement
 
 
December 2022
 
Improvements at Oceano Elementary
 
 
November 2022
 
 
Branch Elementary new MPR
 
 
September 2022
 
Grover Heights new MPR
 
 
June 2022
 
Patient Care Ribbon Cuttings
 
 
 
August 2022
 
facilities update
 
May 2022
 
facilities update
 
March 2022
 
facilities update
 
December 2021

facilities update
 
 
November 2021

facilities update
 
 
October 2021
 
New Patient Care classrooms are going in at AGHS and NHS
 
 
September 2021
 
Branch Elementary getting a facility upgrade
 
 
August 2021
 
 
Dana Elementary getting an upgrade
 
 
 
May 2021
 
 
 
Summer construction projects
 
 
 
 
 
List of Projects
Series 1 Bond Projects
 
Series 1 Projects B
 
Series B Projects
List of projects for Series C
February 2021
Measure I, Improvements at Shell Beach Elementary
 
 
Measure I Stadium Improvements
 
January 2021
 
November 2020
June 2019
 
The new music building at Arroyo Grande High School is complete!!  The new building will house our band and choir programs. 

 

 

 

Oceano Elementary

 

And at Grover Beach Elementary, the 9 new classrooms and restrooms are are nearing completion.  Everyone got a chance to check out what the new rooms will look like this week. The goal is to have teachers in their new classrooms when we return from winter break.

Row of new classrooms

 

New GB Classroom

 

November 2018
 
 
 Harloe Elementary
 
New Harloe Buildings
 

Harloe Elementary had new classrooms delivered and craned into place.  There are seven classrooms and a restroom. Now that the buildings are in place, workers hope to have them all finished and ready for use in the Spring.  The new classrooms are all made possible by Measure I.

September 2018

 

Fairgrove Thank You note

Recently Fairgrove Elementary held a lunch for the Facilities, Maintenance, and Operations team as a thank you for all of their hard work.  The students created thinking maps, thank you notes, and they even stopped by in person to thank the staff. The school is loving their new outdoor learning center and the recent improvements to the school.


Meanwhile there have been some big changes at Grover Beach Elementary as the new modular classrooms move onto campus. Exciting things are happening across the district. We thank the hard working FMO team for all of their dedication!

 
Summer 2018 Projects

 

District-Wide Phone System Upgrade

Arroyo Grande High School
AGHS Music Bldg Demo
AGHS Music Bldg
AGHS Asphalt Replacement

Mesa Middle School
Mesa Re-Roofing Project
Mesa Demo for Relos Move

Dana Elementary
Dana Sewer Upgrade
Dana Covered Walkway Restoration
Dana - replace front entrance gate

Fairgrove Elementary
Fairgrove Utility Upgrade
Fairgrove Site Upgrades

Grover Beach Elementary
GB Re-Roofing Project
GB Foundation/Site Work
GB Asphalt Replacement
GB Modular Bldgs

Harloe Elementary
Harloe Relocatable Move
Harloe Modular Foundation/Site Work
Harloe Modular Bldgs

Nipomo Elementary
Nipomo Relocatable Move
Nipomo ES Shade Structure install
Nipomo ADA/Concrete upgrade
Nipomo Underground Utility Project
Nipomo Relo Classroom/Restroom Demo
Nipomo Asphalt Replacement
   FALL
Nipomo ES Site Work of Relo Temp Housing  
Nipomo ES Site work for Modular Bldgs  
Nipomo ES Modular Bldgs  

Oceano Elementary
Oceano Modular Foundation/Site Work
Oceano Modular Bldgs
Ocean View Elementary
Ocean View OLC/Asphalt
Ocean View Shade Structure install

Paulding Middle School
Paulding Gym Heater Replacement
PMS Gym bowstring truss eval / repair
    FALL 
PMS Retaining wall & staff parking lot  

April 2018
 
March 2018
Nipomo High School's Agriculture Island Opens! 
 
Ribbon Cutting of Ag Island
 
 
 
Watch the construction take place in the video below.
February 2018
 
Mesa Shade Structure
 

The Board of Education approved the Measure I Series B Project list at the regular meeting on February 6, 2018. The projects approved in Series A and B represent just under 50% of the total Measure I funding. A summary of Series A and B projects are listed below:


Replacing Portables with Modular Classrooms: BR, DA, GB, HA, NI EL, OV, OC, JU, ME, PA, AGHS, NHS

Construction of new Multi-Purpose Rooms: BR, GH, SB

Construction of New ‘Learning Commons’ (a shared, modern Library/Lab): GH, SB

Shade Structures: LA, ME

Outdoor Learning Centers: FA, OV

Parking Lot expansion/redesign: JU, SB

New CTE Facilities: NHS

Stadium Upgrades: AGHS, NHS

Modernization of Permanent Classrooms: GB, NI EL, OC, JU

Flexible Furniture: LA, NHS

Auxiliary Gymnasium/Multi Use Facility: AGHS

 

In addition to these site specific upgrades, all sites have recently benefited from the Network Redesign/WIFI project, and a new phone system is being planned for later in 2018. Additionally, multiple sites will be experiencing upgrades such as: ADA access improvements, rip and replacement of failing asphalt/concrete, new roofing, and significant underground utility/power upgrades.

 

We are pleased to have accomplished significant upgrades quickly, and we look forward to a busy, rewarding 2018-2019 calendar year as we finish Series A projects and begin Series B work.

September 2017
NHS Ag Island Groundbreaking

Nipomo High School hosted an official groundbreaking for their new career technical education buildings.  The construction project includes three new classrooms and a workshop for the ag classes. With shovels in hand, School Board Trustees Vicki Meagher, Chad Robertson and Dee Santos joined Superintendent Raynee Daley, Principal John Denno, FFA Chapter President Kyler Vernon and local dignitaries to launch the project.  That is our own Dr. Daley behind the controls of an excavator. Construction is expected to be completed by early next year. Both staff and students are excited about the new buildings and the opportunities that the new facilities will bring.

January 2018

Portable demolition

Lucia Mar made the decision to break the Measure I general obligation bond sale into four bond sales spaced roughly two years apart. This will keep the tax rate in the $41 per $100,000 assessed valuation range for our local property owners. The first issuance of $35,000,000 is being put to work right now through a host of different projects district-wide, many of which are underground infrastructure upgrades. While we are all very eager to see upgrades sooner than later at our sites, our cash flow from bond sales requires that we roll-out our work over time. On our current trajectory, the final projects funded through Measure I will likely occur in the 2025-2026 school year. We are pleased to report that one of our oldest schools, Grover Beach Elementary (constructed in 1955) was the first site to see demolition of old portable classrooms over Winter Break.

 

December 2017

Portable at Grover Beach


The process of replacing portable classrooms with modular construction has begun at Grover Beach Elementary. Nearly every school site will go through this process in the coming years, thanks to Measure I’s funding stream.


Beginning Winter Break, and ending in Summer Break 2018, nine old portables at Grover Beach Elementary will be removed. Once removed, the General Contractor will run utilities, pour concrete, and prepare the site for the arrival of the new classrooms. (Classrooms are moving to temporary portables until the new classrooms are finished.) Teachers currently in these portables will be guided through these steps by Pete Sanchez, recently promoted Project Manager:


-Box and label classroom belongings

-Moving company comes in to move boxes and furniture into leased portables to be used as temporary housing

-Teachers unpack belongings in new, short term classroom


This process will repeat itself as the teachers move into their newly constructed classrooms. Per contract, teachers will receive either three days of substitute support or the equivalent in pay ($115 x 3) each time they are required to move. We fully understand and appreciate the burden these moves will place on our staff, and are committed to supporting our people to the highest level possible through regular communication and assistance.

More projects in gallery below
May 2019
 
Nipomo Elementary is getting new classrooms